Application Recommendations
Try these recommendations on your next cutting job.
Saw cut control joints using the Soff-Cut System. Cut as soon as the slab will
support the weight of the saw and operator, without disturbing the final finish,
normally from 0 to 2 hours after final finish at each control joint. Replace
the Soff-Cut Skid Plate with each new Soff-Cut blade to avoid spalling and raveling.
Use Soff-Cut joint protectors at saw-cut intersections prior to cross-cutting
in order to prevent the corners from breaking down.
If ambient temperature allows, cutting may begin before the curing application
to control shrinkage stress. Remove dry powder by vacuum or light sweep and follow
specified cure procedures. Protect the edge of cuts if using wheeled equipment
within the first 24 hours.
Cold weather concrete placements may extend the initial start of control joint
installation. To ensure desired performance, test cut 2 to 8 lineal feet (1.22
meters to 1.83 meters) at proper depth. If desired results are achieved, continue
to complete balance of cuts at control joint locations.
It is very important to always change the anti-ravel Skid Plate with each new
Soff-Cut blade or chipping and spalling of the joint will result. The spacing
between the blade and Skid Plate becomes greater as the blade cuts the concrete.
Use only Soff-Cut products to ensure proper performance.
|